Alberta Agriculture & Irrigation Main Canal Repair: March 25, 2024
March 25, 2024
The Board has received the following update information with respect to the Main Canal Repair:
Work to date:
• Total excavation of existing gravel armour completed is 3,720m (100%)
• 3,720m of RPE liner in place (100%)
• 3,320m of gravel armour fully placed (89%) (approximately 400m partially covered)
Work over the next two weeks:
• Start toe berm/back slope clean-up work beginning March 25th, this includes final site cleanup and restoration work
• Hauling gravel armour and removing gravel armour from site
• Place 400m of gravel armour layer along the south embankment (Total of 3,720m installed by March 28th)
• Modification of existing siphon (completion by March 28th)
• Removal of the cofferdam (Completion by March 28th)
Work of the project remaining:
• All in canal works (armour, liner sand, etc.)
• Topsoil Placement/Seeding/Remediation
• Toe berm/backslope cleanup
• Site Clean Up
• Placing road gravel on canal bank roads
• Restoring the access roads
• Demobilization
• Weed Control
Milestone dates:
• Substantial Completion – March 31st, 2024 (complete all in-canal work)
• Total Completion – May 31st, 2024 (complete all work of the project)
An update on the water storage as of March 25th, 2024; the Oldman Dam is at 32% of full supply level (FSL) and Keho Reservoir is at 84% of FSL.