Alberta Agriculture & Irrigation Main Canal Repair: March 1, 2024
April 1, 2024
The Board has received the following update information with respect to the Main Canal Repair:
Work to date:
• Total excavation of existing gravel armour completed is 3,450m (93%)
• 3,070m of RPE liner in place (83%)
• 3,000m of gravel armour fully placed (81%)
Work over the next two weeks:
• Hauling gravel armour, sand, and removing gravel armour and liner from site
• Excavate another 270m of gravel armour (total of 3,720m excavated by March 14th)
• Install 430m of RPE liner and geotextile (total of 3,500m installed by March 14th)
• Place 400m of gravel armour layer on top of the liner (total of 3,400m installed by March 14th)
Work of the project remaining:
• All in canal works (armour, liner sand, etc.)
• Modification of existing siphon
• Topsoil Placement/Seeding/Remediation
• Site Clean Up
• Placing road gravel on canal bank roads
• Restoring the access roads
• Demobilization
• Weed Control
Milestone dates:
• Substantial Completion – March 31st, 2024 (complete all in-canal work)
• Total Completion – May 31st, 2024 (complete all work of the project)
An update on the water storage as of March 1st, 2024 is the Oldman Dam was at 30% of full supply level (FSL) and Keho Reservoir was at 84% of FSL.