Alberta Agriculture & Irrigation Main Canal Repair: March 19, 2024
March 19, 2024
The Board has received the following update information with respect to the Main Canal Repair:
Work to date:
• Total excavation of existing gravel armour completed is 3,700m (99%)
• 3,610m of RPE liner in place (97%)
• 3,200m of gravel armour fully placed (86%)
Work over the next two weeks:
• Hauling gravel armour, sand, and removing gravel armour and liner from site
• Excavate another 20m of gravel armour (total of 3,720m excavated by March 22nd)
• Install 110m of RPE liner and geotextile (total of 3,720m installed by March 22nd)
• Place 520m of gravel armour layer on top of the liner (total of 3,720m installed by March 22nd)
• Piezometer installation (all additional piezometers installed by March 18th)
• Modification of existing siphon (completion by March 22nd)
• Removal of the cofferdam (Completion by March 28th)
• DD plans to start the toe berm/back slope clean up work beginning on March 25th. This includes final site clean up and restoration work.
Work of the project remaining:
• All in canal works (armour, liner sand, etc.)
• Topsoil Placement/Seeding/Remediation
• Toe berm/backslope cleanup
• Site Clean Up
• Placing road gravel on canal bank roads
• Restoring the access roads
• Demobilization
• Weed Control
Milestone dates:
• Substantial Completion – March 31st, 2024 (complete all in-canal work)
• Total Completion – May 31st, 2024 (complete all work of the project)
An update on the water storage as of March 19th, 2024; the Oldman Dam is at 31% of full supply level (FSL) and Keho Reservoir is at 84% of FSL.