Alberta Agriculture & Irrigation Main Canal Repairs: April 8, 2024
April 8, 2024
The Board has received the following update information with respect to the Main Canal Repair:
Work to date:
• Total excavation of existing gravel armour completed is 3,720m (100%)
• 3,720m of RPE liner in place (100%)
• 3,720m of gravel armour fully placed (100%)
• Siphon modification to toe berm
• Removal of the cofferdam
Work over the next two weeks:
• Site cleanup, demobilization of job shack and several pieces of equipment
• Dennis Dirtworx plans to start the toe berm/ back slope clean-up work beginning on April 8 after the snow melts. This includes:
o Topsoil Placement/Seeding/Remediation
o Toe berm/backslope cleanup
o Drain outlet modifications
o Canal net test to be conducted April 15 & April 16
Work of the project remaining:
• Placing road gravel on canal bank roads
• Restoring the access roads
• Final Demobilization
• Weed Control
Milestone dates:
• Partial Substantial Completion – March 28th, 2024 (complete all in-canal work)
• Total Completion – May 31st, 2024 (complete all work of the project)
An update on the water storage as of April 8, 2024; the Oldman Dam is at 34% of full supply level (FSL) and Keho Reservoir is at 84% of FSL.